Project description

The scope of this project was engineering, fabrication en installation of mesh fabric sunscreen at the OCC-building at the KLM-site in Schiphol-East. 

After the dismantling of existing steel plate façades, a façade construction was delivered and installed. The mesh fabric sunscreens were fitted onto the new façade construction, this on the 4 sides of the building all in various dimensions. 

TYPE OF PROJECT

Revitalizing building 

CLIENT

PolyNed commissioned by Sodexo 

LOCATION

Amsterdam

PURPOSE

Flight Operations Control Center 

COMPLETED

100 % completed: 24.01.2019

TYPE OF CONTRACT

Subcontractor 

DURATION

Total 105 working days 

Realised:

KLM OCC Schiphol Amsterdam

KLM OCC SCHIPHOL

Projectomschrijving

Dit project bestond uit engineering, fabricage en montage van een gaasweefsel zonwering op het OCC-gebouw op het KLM-terrein te Schiphol-Oost.

Na het demonteren en van bestaande staalplaten gevel is er een gevelconstructie geleverd en geplaatst. Op deze nieuwe gevelconstructie is een gevel gaasdoek afgemonteerd, dit op de 4 zijden van het gebouw in diverse afmetingen rondom het gebouw.

TYPE PROJECT

Revitaliserend bouwen 

OPDRACHTGEVER

PolyNed iov Sodexo 

PLAATS

Amsterdam

GEBRUIKSFUNCTIE

Flight Operations Control Center 

GEREALISEERD

100 % gerealiseerd: 24.01.2019

CONTRACTVORM

Onderaannemer

DOORLOOPTIJD

Totaal 105 werkdagen

Gerealiseerd: